ContractorApprovalsTotal stated
City of American Canyon1$2.1M
SoCal Pacific dba National Coating and Lining1$1.9M
Piazza Construction1$1.3M
North Bay Excavation, Inc.2$725,383
FBD Vanguard Construction, Inc.1$676,229
Rege Construction1$602,598
Titans Group Corporation1$532,261
American Road Maintenance1$470,380
Roebbelen Contracting, Inc.1$374,028
Weeks Drilling and Pump Company1$289,975

Amounts as stated in the item (often a not-to-exceed maximum); agreements without an amount count without one.

$374,028Meeting Oct 6, 2026

Roebbelen Contracting, Inc.

Award of Construction Contract for the Wildlife Exclusion Perimeter Fence Phase 2 -

Sonoma County Board of Supervisors · Public Infrastructure · Category 2389 Other specialty trade contractors (inferred)

On the agendaSonoma County, CA

B) Find Diamond D Construction LLC’s bid non-responsive and award the construction contract to the lowest responsive and responsible bidder, Roebbelen Contracting, Inc., in the amount of $374,028.40 including the base bid and bid alternate 1.

View the agenda →

Amount not statedMeeting Oct 6, 2026

McCarthy Building Companies, Inc.

preconstruction phase services for the proposed new County Government Center

Sonoma County Board of Supervisors · Public Infrastructure · Category 2362 Nonresidential building construction (inferred)

On the agendaSonoma County, CA

A) Award a contract for Construction Manager at Risk (“CMAR”) to McCarthy Building Companies, Inc. (“McCarthy”) for preconstruction phase services for the proposed new County Government Center (“CGC”) project (“Project”), and delegate authority to the Director of the Department of Public Infrastructure to execute the contract in a form approved by County Counsel.

View the agenda →

$2.1M maxMeeting Sep 15, 2026

City of American Canyon

construction services, inspections and materials testing for the South Kelly Road and Tower Road Paving Project, RDS 25-16

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

Q. Approve and authorize Agreement No. 270159B with the City of American Canyon for a maximum of $2,149,156 for construction services, inspections and materials testing for the South Kelly Road and Tower Road Paving Project, RDS 25-16; and

View the minutes → · Agreement 270159B

$1.9MMeeting Sep 15, 2026

SoCal Pacific dba National Coating and Lining

the Sonoma Tank No. 1 Recoating Project

Sonoma County Board of Supervisors · Sonoma County Water Agency · Category 2383 Painting & coating contractors (inferred)

ApprovedSonoma County, CA

B) Award the contract to SoCal Pacific dba National Coating and Lining for $1,894,140 for the Sonoma Tank No. 1 Recoating Project and authorize the Chair to execute the contract.

View the agenda →

$470,380Meeting Sep 15, 2026

American Road Maintenance

Award of Construction Contract for the Apron E and Portions of Runway 14/32

Sonoma County Board of Supervisors · Public Infrastructure · Category 2373 Highway, street & bridge construction (inferred)

ApprovedSonoma County, CA

B) Award the construction contract to the lowest responsive and responsible bidder, American Road Maintenance, in the amount of $470,380.

View the agenda →

Amount not statedMeeting Sep 15, 2026

Midstate Barrier, Inc.

the 2026 Annual Guardrail Repair, RDS 26-12

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

T. Award a Construction Contract to Midstate Barrier, Inc. for the 2026 Annual Guardrail Repair, RDS 26-12, and approve a Budget Amendment. (Fiscal Impact: $594, 879 Expense for the construction contract and other project costs; SB-1 Non-Operating Special Revenue Fund; Not Budgeted; Discretionary) [4/5 vote required] 26-1670 26-1388 26-1638 26-1649 26-1656 Board of Supervisors Meeting Minutes September 15, 2026 Page 6 of 12

View the minutes →

$676,229Meeting Aug 11, 2026

FBD Vanguard Construction, Inc.

Award the construction contract for the HSIP Cycle 11 Silverado Trail

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

M. Award the construction contract for the HSIP Cycle 11 Silverado Trail Intersection Improvements Project (RDS 22-26) to FBD Vanguard 26-1427 Construction, Inc. in the amount of $676,229;

View the minutes →

$238,663Meeting Aug 11, 2026

CRE Construction Group, Inc.

the “Napa Library Building Maintenance Project,” PW 25-13A

Napa County Board of Supervisors · Public Works · Category 2362 Nonresidential building construction (inferred)

ApprovedNapa County, CA

O. Award of Construction Contract to CRE Construction Group, Inc. of Granite Bay, California in the amount of $238,663 for the “Napa Library 26-1548 Building Maintenance Project,” PW 25-13A. (Fiscal Impact: $238,663, Library Fund; Budgeted; Discretionary)

View the minutes →

$158,325Meeting Aug 11, 2026

North Bay Excavation, Inc.

the “Redwood Road MPM 5.41 Project,” RDS 26-22

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

N. Award a Construction Contract to North Bay Excavation, Inc., of Valley Ford, CA in the amount of $158,325 for the “Redwood Road MPM 5.41 26-1536 Project,” RDS 26-22. (Fiscal Impact: $234,906 Expense for the construction contract and other project costs; General Fund, Reallocation of Budget; Discretionary)

View the minutes →

$289,975Meeting Aug 4, 2026

Weeks Drilling and Pump Company

construction of the Demuth Property Test Well

Sonoma County Board of Supervisors · Category 2371 Utility system construction (water, sewer, pipeline) (inferred)

ApprovedSonoma County, CA

B) Award the contract to Weeks Drilling and Pump Company for $289,975 for construction of the Demuth Property Test Well and authorize the Chair to execute the contract.

View the minutes →

$1.3MMeeting Jul 28, 2026

Piazza Construction

the “Mt Veeder Road MPM 4.3 and MPM 3.25 Project, RDS 26-24”

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

AH. Award a Construction Contract to Piazza Construction of Penngrove, California, in the amount of $1,268,000 for the “Mt Veeder Road MPM 26-1429 4.3 and MPM 3.25 Project, RDS 26-24”. (Fiscal Impact: $2,220,799 Expense for the construction contract and other project costs; General Fund, Reallocation of Budget; Discretionary) Board of Supervisors Meeting Minutes July 28, 2026 Page 8 of 12

View the minutes →

$602,598Meeting Jul 28, 2026

Rege Construction

the “White Sulphur Spring Rd Slide Repair”, RDS 26-37

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

AB. Award of Construction Contract to Rege Construction, of Cloverdale, CA in the amount of $602,598 for the “White Sulphur Spring Rd Slide 26-1378 Repair”, RDS 26-37 (Project 26027); and

View the minutes →

$567,058Meeting Jul 28, 2026

North Bay Excavation, Inc.

the “550 Wall Road Landslide Repairs Project”, RDS 26-38

Napa County Board of Supervisors · Public Works · Category 2373 Highway, street & bridge construction (inferred)

ApprovedNapa County, CA

AC. Award of Construction Contract to North Bay Excavation, Inc. of Valley Ford, California in the amount of $567,058 for the “550 Wall Road 26-1412 Landslide Repairs Project”, RDS 26-38 (Project 26028); and

View the minutes →

$532,261Meeting Jul 28, 2026

Titans Group Corporation

the “Napa County Animal Shelter Phase I Roof Repair,” PW 26-05A

Napa County Board of Supervisors · Public Works · Category 2381 Roofing & structural contractors (inferred)

ApprovedNapa County, CA

AD. Award of Construction Contract to Titans Group Corporation of Escondido, California in the amount of $532,261 for the “Napa County 26-1414 Animal Shelter Phase I Roof Repair,” PW 26-05A; and

View the minutes →

$199,738Meeting Jul 28, 2026

Peters Excavating, Inc.

the “Pueblo Area Ditch Project, RDS 25-36”

Napa County Board of Supervisors · Public Works · Category 2371 Utility system construction (water, sewer, pipeline) (inferred)

ApprovedNapa County, CA

AG. Award a Construction Contract to Peters Excavating, Inc. of Sebastopol, California in the amount of $199,738 for the “Pueblo Area Ditch Project, 26-1424 RDS 25-36”. (Fiscal Impact: $349,999 Expense for the construction contract and other project costs; Accumulated Capital Outlay; Reallocation of Budget; Discretionary)